ELEMENTARY SCHOOLS

 
Lakeside Elementary School
Proposed Work
  • HVAC Upgrades: New Boilers + Air Conditioning 

  • Electrical Service Upgrades

  • Roof Replacement

  • LED Lighting

  • New Early Childhood and Kindergarten Classrooms

  • Interior Refresh 

  • Parent + Bus Drop-Off/Pick-Up Improvements

  • New Parking Lot

  • Playground Relocation with ADA Accessibility

  • Renamed Bunker Elementary

Two-Way Immersion Program at
Glenside Elementary School
Proposed Work
  • HVAC Upgrades: New Boilers + Air Conditioning Throughout Building

  • Roof Replacement

  • LED Lighting Throughout Building

  • Interior Refresh 

  • Relocated Office with Secure Vestibule

  • Electrical Service Upgrade

  • Playground Renovated with Age-Appropriate Equipment

Marquette Elementary School
Proposed Work
  • HVAC Upgrades: New Boilers + Air Conditioning

  • Electrical Service Upgrades 

  • Roof Replacement

  • LED Lighting

  • Interior Refresh 

  • New Office with Secure Vestibule

  • Playground Renovation with Age-Appropriate Equipment

​Proposal Two Project:

  • Exterior Refresh

Oakview Elementary School
Proposed Work
  • HVAC Upgrades Throughout Building: New Boilers + Air Conditioning 

  • Electrical Service Upgrades

  • Roof Replacement

  • LED Lighting Throughout Building

  • Interior Refresh 

  • Parent + Bus Drop-Off/Pick-Up Improvements

  • Playground Renovation with ADA Accessible Equipment

  • Complete Remodel of the Oldest  Section of the Building into Early Childhood Classrooms

 

MIDDLE SCHOOL

Charles Hackley Middle School
Proposed Work
  • New Charles Hackley Middle School on the former Mercy Hackley Hospital Campus site 

  • Steele Building would be closed and repurposed into vacant land once construction on the new school is completed 

  • Track and Field at the Steele Building site will remain intact

​Proposal Two Projects:

  • Option for New Track and Soccer/Athletic Field

HIGH SCHOOL

 
Proposed Work

Muskegon High School

  • HVAC Upgrades: Heating + Air Conditioning

  • Roof Replacement

  • LED Lighting 

  • Interior Refresh 

  • Electrical Service Upgrade

 

Redmond Potter Building

  • HVAC Upgrades: Boiler Replacement

  • Roof Replacement

  • LED Lighting

  • Electrical Service Upgrade 

 

J - Building

  • Building Removed

​Proposal Two Projects:

  • New 84’ Single Court Gymnasium Connecting the High School and Redmond Potter Building

  • New Secure High School Entrance 

  • Additional Parking for Campus

  • Swimming Pool Refresh and New Equipment

  • Fine Arts Equipment Upgrades

  • Hackley Stadium - Turf Field 

  • Replace Bleachers in Redmond Potter Gym

  • Security Focused Campus Reorientation

Proposed Work

Hackley Stadium

  • HVAC Upgrades: Boiler Replacement

  • Electrical Service Upgrade

 

Campus Power Plant

  • Building Removed

Manual Building

  • HVAC Upgrades: Heating + Air Conditioning 

  • Roof Replacement

  • LED Lighting

  • Electrical Service Upgrade